OBS @ Coney Island - DFMA Modular Lead-in Pipes

aliciaek

Tiong Seng has successfully achieve more than the set target of 100m a day of DfMA modular lead-in pipes installation.

The total length spans 2200m and 950m has been installed within 7 working days (as of 17 July 2022) with a team configuration of 3 personnel, including an excavator operator and lifting supervisor.




 
 
 